Part 3 of 5 Parts (Please read Part 1 and 2 first)
GEH and TerraPower are also part of a team led by Bechtel National Inc. that was recently selected by Battelle Energy Alliance (BEA) to lead the design and construction phase of the DoE’s Versatile Test Reactor (VTR), a one-of-a-kind research facility designed to give U.S. companies access to fast spectrum irradiation testing. Negotiations are continuing for that contract.
GEH and TerraPower had previously collaborated to provide a conceptual design for the VTR project that incorporated GEH’s PRISM technology. Kemal Pasamehmetoglu is executive director of the VTR project. He said that the VTR is awaiting Critical Decision-1. It will probably be a 300-megawatt sodium-cooled pool-type fast reactor based on the PRISM design that will use fuels with metallic alloys, including high-assay low-enriched uranium fuel (HALEU).
Pasamehmetoglu is confident that technical implementation of the test reactor does not poses a challenge. He did mention that although the DoE has pushed for a 2026 completion date to allow a wide range of advanced and existing nuclear technology developers to test their concepts, the project’s time completion hinges on Congressional appropriations.
The two hundred and ninety-five million dollars requested by the DoE in fiscal year 2021 to kick off the project remains uncertain. Funding delays could push the project’s completion to 2031. That would constitute a significant hurdle for an array of advanced nuclear developers who are banking on the facility to commercialize their technologies in the late 2020s.
Pasamehmetoglu mentioned that the only viability for testing fast spectrum irradiation currently accessible to U.S. companies is the BOR-60 reactor in the Russian Federation. The BOR-60 fast neutron reactor is one of the key experimental facilities in the world able to perform large-scale tests of fuel, absorbing, and structural materials for advanced reactors. It was put into operation in December of 1969. Although it was supposed to be retired in 2014, a great deal of work has been done in the past few years to justify continuing operation. However, the use of the BOR-60 reactor does have some problem for U.S. companies including export control concerns for materials and fuels testing, intellectual property rights, quality assurance and transportation issues.
Pasamehmetoglu went on to say, “Existing test reactors, like the Advanced Test Reactor at Idaho National Laboratory and the High Flux Isotope Reactor at Oak Ridge National Laboratory, are thermal neutron reactors and are not capable of sustaining neutrons at concentrations and speeds high enough to perform accelerated testing of innovative nuclear technologies under development.”
The VTR urgency is highlighted by an Advanced Reactor Demonstration Program funding award opportunity (FOA) released by the DoE last May to provide one hundred and sixty million dollars to the U.S. nuclear industry in the first year of funding for the construction of two reactors that can be operational within the next five to seven years. The period to submit applications to the FOA closed on August 19th of this year. A selection of the demonstration pathway award (or awards) is likely in October of 2020.
Please read Part 4 next